GreenFrog Seoul Blog Episode 107 Β·

The delay was caused by a typhoon
Force majeure clauses in China factory contracts - what qualifies and what does not, CCPIT certificates, notice deadlines, loss allocation, and when you can terminate

Hello, this is GreenFrog Seoul.

Ten days before shipment, a WeChat message arrives from the factory. "The typhoon shut us down for two days. This is force majeure, so we need to push delivery back three weeks."

That one line bundles several things together. The typhoon happened, that much is true. The factory probably did lose two days. But why two lost days turn into a three-week delay, and who absorbs the losses those three weeks create, are entirely separate questions. If you have no answer to them, you end up accepting whatever number the factory named.

That is what today is about. A force majeure clause is not there to settle whether something went wrong. It is there to decide in advance who carries how much of the loss when it does. It sits as a paragraph in the contract that nobody reads for years, until the one moment when everything is urgent and you suddenly need it.

The overall skeleton of a contract was covered in Episode 12, and purchase orders and production tracking in Episode 102. Today we look at the machinery that engages when that contract stops running to plan.

Importers usually lose force majeure disputes not because they argued "that was not force majeure" and lost. They lose because the moment they accept that it was force majeure, the contract has no sentence saying what is excused next and what is not. The typhoon is not the factory's fault, but who pays the air freight the typhoon created is still entirely up for negotiation.

A note on scope This article reflects contract practice with Chinese factories as of September 2026. The notice deadlines, duration caps and cost-sharing ratios used below are representative figures and examples meant to explain the mechanics; actual terms shift with the product, the contract structure, the governing law and each side's leverage. Force majeure turns on legal judgment and the outcome moves with the facts, so if the contract value is large or a dispute has already started, talk to a lawyer who handles international trade first.

1. What force majeure really decides is the scope of the excuse

When someone says "this is force majeure," most people hear it as: something unavoidable happened, so the factory is off the hook. That is only half right.

Where force majeure applies, the factory is released from liability for performing late. It is no longer in breach, and it owes no liquidated damages. All of that is correct. But in practice the money almost always sits outside that boundary.

A three-week slip kills the selling window on a seasonal product. If a TV shopping slot was booked, there is a penalty. If you took online pre-orders, refunds go out. Switch to air freight to catch up and you pay five times the ocean rate. These costs land whether or not force majeure is established. What the clause decides is who ends up holding them.

So move the focus of the negotiation. Arguing about whether the typhoon really happened is usually pointless. It happened. The questions worth asking are different ones.

If those four points are already written into the contract, the day the incident hits you are confirming, not negotiating. If they are not, you start negotiating from zero at the most chaotic possible moment, with the goods sitting in their factory and the urgency on your side. That is a bad seat.


2. What counts as force majeure and what does not

A factory saying the words "force majeure" does not make it so. Sort the reasons you actually run into by character and the line is fairly clear.

CauseForce majeure?Where it gets decided in practice
Typhoon, flood, earthquake, heavy snowUsually yesWhether that area actually took damage, and whether the delay matches the scale of it
Government power rationing (限甡)Usually yesWhether the local government notice exists, and whether its area and dates cover your factory
Shipment barred by export controls or sanctionsYesWhether the measure was already announced when the contract was signed
Port closure or large-scale strikeUsually yesWhether an alternative port was available
Lockdown measures from an epidemicConditionalWhether the administrative order, rather than the illness itself, blocked performance
Raw material price spikeUsually noMore expensive is not the same as unobtainable
Sharp currency moveNoTreated as commercial risk
Factory cash shortage or insolvencyNoInternal circumstances fall in the avoidable category
Labor shortage, skilled workers leavingNoManagement risk
Equipment breakdownUsually noMaintenance is the factory's responsibility
Incident at a subcontractorConditionalWhether what happened to that subcontractor is itself force majeure
Fire at the factoryConditionalWhether the cause was external or poor management

The rows in bold are where most real disputes live. The sixth one in particular, a factory claiming force majeure because raw material prices jumped, comes up constantly.

The test here is simple. Copper is up 40% and the factory loses money at this unit price: that is the factory's problem, not an inability to build. Performance is still possible. If instead the government bans distribution of a material and there is genuinely none on the market, that is a different story. The line runs between more expensive and unobtainable.

Take a subcontractor incident in two steps When a factory says "our component supplier could not deliver, so we cannot build," that alone is not force majeure. Selecting and managing suppliers is the factory's job, and there is usually room to source elsewhere. It changes if an earthquake hit that supplier's region, collapsed its plant, and the part only comes out of a dedicated tool. First ask whether what happened to the subcontractor meets the force majeure test on its own, then ask whether alternative sourcing was possible. It has to clear both steps before it tilts toward an excuse.

3. The three-part test under Chinese law versus an Anglo-American clause

This is where a lot of people get tangled up. Contracts with Chinese factories are usually in English with clauses drafted in the Anglo-American style, but when a dispute breaks out the governing law is often Chinese law. The two systems work differently.

Chinese law: it applies even with no clause

The Chinese Civil Code defines force majeure as an objective circumstance that is unforeseeable, unavoidable and insurmountable. All three have to be satisfied. And there is one more thing that matters: because this is a statutory definition, it applies even if your contract contains no force majeure clause at all.

If you have been thinking "we left force majeure out of our contract, so the factory is liable no matter what," look again. Where Chinese law governs, statutory force majeure comes in on its own. Omitting the clause does not remove the excuse; it leaves you with the bare statute and no notice deadline, no evidence requirement and no duration cap. None of that helps you.

Force majeure under Chinese lawAnglo-American contract clause
BasisDefined in statuteWhatever the contract says, and nothing more
If there is no clauseThe statutory definition appliesIn principle, no excuse at all
TestUnforeseeable, unavoidable, insurmountableWhether it falls within the listed causes
List of causesNo specific list; judged case by caseUsually a long list plus a catch-all phrase
EffectLiability excused to the extent of the impact, in whole or in partWhatever effect the clause specifies
Notice obligationNotify without delay and submit evidenceThe deadline and method written into the clause

The useful conclusion is this. Treat the contract clause not as a way to switch off statutory force majeure, but as a way to shape how it applies in your favor. Narrow what counts as a cause, force notice within a set number of days, specify the evidence required, and give yourself a termination right once it runs past a certain point. None of those four exist in the statute, so they exist only if you put them in the contract.

Applying the three-part test to real situations

Unforeseeable, unavoidable and insurmountable sound abstract, but held up against a concrete case they separate more cleanly than you would expect.

When a factory claims force majeure, the third element is usually where you have room to dig. You cannot undo the typhoon, but you can ask as many questions as you like about what the factory did after it.


4. How to read a CCPIT force majeure certificate

The China Council for the Promotion of International Trade (CCPIT, δΈ­ε›½ε›½ι™…θ΄Έζ˜“δΏƒθΏ›ε§”ε‘˜δΌš) issues a certificate attesting to force majeure facts. It became widely known when they were issued in volume during COVID, and factories still attach one now and then when notifying a delay.

The document arrives with an official seal on it, which carries a certain weight. Once you know precisely what it certifies, the reaction changes.

What the certificate coversWhat it does not cover
FactsThat the event occurred at a given time and placeThat the event blocked performance of this contract
CausationNoneThe link between the event and the length of the delay
Legal effectOne piece of supporting evidenceA decision on whether liability is excused
Depth of reviewConfirmation based on submitted documentsSite inspection or review of alternatives
ScopeThe contract the applicant namedA blanket excuse covering every customer

The right-hand column is the point. The certificate confirms that the event happened in that area. It does not confirm that this factory therefore could not perform this contract. Causation and the reasonableness of the delay period are still things the factory has to establish separately.

Check three things when a certificate arrives First, the gap between the event period on the certificate and the delay the factory is claiming. A five-day lockdown against a four-week delay means the remaining three weeks need their own explanation. Second, whether the area named on the certificate matches where the factory actually sits. Measures frequently differed city by city within the same province. Third, whether your contract is identified in the certificate application. Factories do recycle a certificate obtained for a different order.

Just remember that a certificate landing in your inbox does not end the negotiation. It is a starting point, not a conclusion. And the reverse holds too: no certificate does not mean no force majeure. Local government notices, meteorological records and other objective evidence establish the same thing perfectly well.


5. The notice obligation and its deadline - where the excuse breaks most often

The most powerful part of a force majeure clause in practice is the notice provision. However carefully you draft the list of causes, without a notice clause the factory tells you whenever it suits them; with a tight one, simply failing to notify on time shakes the whole claim.

What changes when notice is late

The pattern we see repeatedly runs like this. Regional power curtailment starts in early August. The factory says nothing, then declares force majeure three days before the delivery date. You had three weeks in which you did nothing, when you could have been pricing air freight, splitting the urgent volume to another factory, or warning your own buyer.

That produces a loss created by the late notice itself. The power cut may not be the factory's fault, but the opportunity you lost because nobody told you in time is. Spell that structure out in the contract and you gain a card to play.

Notice elementWhat to put in the contractWhat happens if you leave it out
DeadlineWithin 3-5 business days of the event"Without delay" alone invites an argument over how many days counts as delay
MethodIn writing (email included), to a designated addressThey claim a one-line WeChat message was notice
Initial evidenceOfficial sources: government notices, weather recordsThey submit nothing but documents they wrote themselves
Scope of impactExpected days of delay and the status of the volume in progressYou get "difficult for a while" and nothing else
Deadline for further evidenceSupporting materials within 15 days of the first noticeThe claim stands with no evidence behind it
Progress reportingA status update at least weeklyOperations resume and nobody tells you, so you cannot plan
Notice of endWithin 3 days of the cause clearing, plus a revised scheduleIt is unclear when liquidated damages start running again
Effect of late noticeLosses enlarged during the delay in notifying are not excusedNotifying late carries no downside at all

The bottom row is the conclusion of the table. Writing that losses enlarged by late notice are not excused works better in practice than writing that missing the notice deadline voids the force majeure claim outright. Factories push back hard on the latter at the negotiating table, and a tribunal may well find it excessive. The former reads as natural logic, and most factories accept it.

Address the notice to an address, not a person "Notify Manager Kim" becomes a problem the moment Manager Kim leaves and a dispute follows. Give a company-level email address together with the responsible department, and add a sentence requiring written notice if the address changes. Designate the factory's sending address too. When a salesperson's WeChat remarks blend into official notices, you get "we already told you" arguments later.

6. What is excused and what is not

Say force majeure is established. What exactly is excused? Leave this boundary blurry and it becomes the biggest fight later.

ItemDefault treatmentIf the contract is silent
Delivery extensionExtended by the period of impactYou argue over how the extension is calculated
Liquidated damages (LD)Waived for the period of impactUnclear when the waiver starts and ends
Liability for breachExcusedRelatively little room for dispute
Deposit already paidNot excused β€” refundable if performance becomes impossibleThe factory holds it to "cover its losses"
Cost of alternative productionIn principle the buyer'sNo basis at all for splitting it
Air freight differentialOpen to negotiationYou bearing all of it becomes the default
Work in progress (WIP) and raw materialsSubject to settlementOnly the factory's own number survives, with no inspection
Your consequential lossesUsually excused as indirect damageHard to claim in the first place
Tooling and buyer-supplied materialsReturned to the ownerThe factory holds them against the outstanding balance

Look closely at the fourth row. Force majeure excuses the obligation to perform; it does not create a new right to keep money already received. If production ultimately becomes impossible and the contract is terminated, the factory keeps only what corresponds to what it actually performed and returns the rest. In practice, though, factories quite often come back with "we took typhoon damage too, so we will keep the deposit against it." The contract needs a sentence that anticipates this.

The sixth row, the air freight differential, carries real weight too. Divert goods that would have taken 40 days by sea onto a plane and the freight multiplies several times over. Nothing in the statute says who pays that difference under force majeure. It is settled purely by the contract and the negotiation. One line β€” "any additional cost arising from a change of transport mode to recover a force majeure delay shall be shared equally by the parties" β€” removes most of the argument when it happens. Losses in transit and insurance claims are a different animal, covered separately in Episode 57.

Your payment obligation usually survives the force majeure period The factory's production obligation being suspended does not automatically suspend yours. The balance on goods already delivered and any installment already fixed stay due. Conversely, if a deposit payment date has not yet arrived, give yourself a basis to push it back. Add a sentence: "any payment falling due during a force majeure period shall be deferred until the cause is resolved." It keeps you from paying out while production sits still. For the broader design of payment timing, read Episode 106 alongside this.

7. The language to actually put in the contract

By now you have a sense of which elements you need. Time to turn them into sentences. Here is a usable skeleton, item by item.

Definition clause - pair the list with exclusions

Listing causes is not enough on its own. Tack "and other similar causes" onto the end and the factory gains room to slot in anything. Write an inclusion list and an exclusion list together.

"Force majeure means an objective circumstance that the parties could not foresee, avoid or overcome, including natural disasters, war, compulsory government measures (including power restriction measures), import or export prohibitions, port closures and large-scale strikes. However, fluctuations in raw material prices, currency fluctuations, the supplier's financial condition, equipment breakdown, labor supply problems and changes in market demand shall not constitute force majeure."

That one exclusion line does a lot of work later. When you are asked for a price increase or a delivery extension because material costs went up, quoting the sentence back keeps the conversation short.

Notice clause - deadline, method and evidence in one sentence

"The party affected by a force majeure event shall give written notice to the other party's designated email address within 5 business days of the date the event occurs, stating the nature of the event, the time it occurred, the volume affected and the expected number of days of delay. Within 15 days of that notice, it shall submit supporting evidence issued by a government authority or a recognized third party. If notice is not given within the above period, no excuse may be claimed for losses that were enlarged during the period the notice was delayed."

Duty to mitigate - the clause most often missing

An enormous number of contracts simply do not have this one. Which is a shame, because it ties directly to the insurmountability element above and therefore carries real force.

"The party claiming force majeure shall take all commercially reasonable measures to minimize its effects, including consideration of alternative production lines, distributed production through partner factories, alternative raw material sourcing and partial shipment. At the other party's request, that party shall explain in writing the measures taken."

The last sentence is the key. With an explanation duty in place, the factory cannot simply say "there was nothing we could do" and move on. It has to write down what it tried, and if what comes back is thin, that thinness is itself negotiating material.

Duration cap and termination right

"If a force majeure condition continues for more than 30 days, the parties shall confer on alternative means of performance. If it exceeds 60 days, either party may terminate all or part of the relevant order by written notice to the other, in which case the deposit paid by the buyer, less an amount corresponding to the portion already performed, shall be refunded within 15 business days of the date of notice."

Deposit refund and settlement

Without a refund deadline attached to the termination clause, you get a promise to return the money and then months of stalling. Write the deadline and the settlement basis together.

"The deduction under the preceding paragraph shall be limited to the actual cost of work in progress and buyer-specific raw materials verified by the buyer, and the seller shall submit material purchase receipts and a work-in-progress status report evidencing the same. The buyer may demand delivery of that work in progress and those raw materials."

If you paid for it, attach the right to collect it That last sentence changes the character of the settlement negotiation. Concede the deduction alone and you have simply lost money; take delivery of the WIP and raw materials the deduction covers and you have something another factory can finish. On an order built with your exclusive fabric or buyer-supplied components, that single line is worth a great deal. The overall structure of the contract is laid out in Episode 12 on OEM/ODM contracts, worth reading alongside this.

8. When it drags on - where do you cut it off

Here is what happens when you leave the duration cap out of a force majeure clause. The factory keeps saying it is "still recovering," you are bound by the contract so you cannot go to another factory, and you cannot get the deposit back either. The longer it runs, the more the loss piles up on your side. A duration cap builds that exit in advance.

Elapsed timeTypical designWhat you should be doing
Up to 7 daysReceive notice, confirm the situationReview the evidence; check whether other factories are running normally
7-30 daysRecalculate delivery, discuss partial shipmentRe-prioritize seasonal volume; give your buyers advance warning
Past 30 daysDuty to confer on alternative performance kicks inSecure quotes from alternative factories; check whether tooling can be moved
Past 60 daysUnilateral termination right arisesDemand settlement documentation; inspect the work in progress
Past 90 daysThe cap used in long-term contractsDecide whether to terminate the annual contract as a whole

Where you set the cap is determined by the product. For strongly seasonal apparel or holiday goods, even 30 days is long β€” past that point the goods arrive and you cannot sell them. For everyday items you sell year-round, 60 or 90 days is fine. Work backward from the date your selling window closes.

What to secure when you terminate

Sending the termination notice is not the end of it. With goods and money still sitting in China, several things need cleaning up.


9. When it is not force majeure but they say it is

This is the situation we run into most often in consultations. Delays caused by something else and dressed up as force majeure outnumber genuine disasters. From the factory's side it is a convenient word that dodges liquidated damages and quiets you down.

What the factory saysWhat is likely going onHow to check
"Regional power curtailment stopped the line"They ran another customer's order first and fell behindRequest a quote from another factory in the same area and see whether it is running
"We cannot obtain the raw material"The price rose and they lose money building itCheck the market price and stock situation for that material independently
"COVID measures left us short of workers"Ordinary turnover or peak-season labor shortageVerify that the public health notice they cite actually exists
"It is our supplier's problem, nothing we can do"They could not pay the supplier, so supply stoppedDemand a written account of the nature of the supplier's reason
"The typhoon closed the port"They missed the booking or were not ready to shipCheck carrier notices and the port's operating status
"A government inspection shut the factory"An administrative penalty for breaching environmental rulesAsk why the order was issued β€” a violation is an avoidable circumstance

The bottom row is the one that splits easily. The government did close the factory, true, but if the cause was exceeding emission limits, the character of it changes. It would not have closed had they followed the rules, so it is an avoidable circumstance. Do not back off at the phrase "government measure" β€” ask what triggered the measure.

Three questions that do the checking for you

There is a way to verify without giving the impression you are accusing anyone. If it is genuinely force majeure, the factory has no trouble answering.

Checking another factory in the same area is the fastest test Whether a measure covers the whole region or is specific to this factory shows up within days if you put a new quote request to other factories there. If they come back with normal delivery dates, the regional-measure explanation is hard to sustain. Keeping two or three alternative factories on file for the same product completely changes how fast you can judge a moment like this. An alternative factory is an information source before it is a negotiating card.

10. Common mistakes

Things that keep coming up in force majeure consultations:


11. Force majeure response checklist

When drafting the contract

Immediately after receiving notice

When deciding how to respond

When moving to termination or settlement


Closing - you can only write the clause before the accident

Suggest reworking a force majeure clause and the usual reply comes back: how often does that really happen? Fair enough. Most orders finish without a typhoon or a blackout anywhere near them.

But the value of this clause is calculated from the amount at stake when it fires, not from how often it fires. Lose the entire selling window because one seasonal run slipped three weeks and that single order costs more than years of contract maintenance. It works like an insurance premium. You pay it in advance hoping never to use it.

There is one more constraint on this clause: timing. You cannot rewrite the wording the day after the typhoon. By then the factory is standing in the stronger position and you are the one who needs something. The clause can only be touched when nothing is wrong, at the moment both sides are pleasantly exchanging a contract.

The order we recommend in practice is this. Open the contract you are using right now and find the force majeure clause. If there isn't one, that is the biggest finding of all. If there is, check four things only: whether the notice deadline is written as a number, whether the duty to mitigate is in there, whether there is a duration cap and a termination right, and whether the deposit refund deadline is stated. More contracts than you would expect are missing two or more of those four.

GreenFrog Seoul reviews contract language with Chinese factories and works alongside importers on the practical response to force majeure and delivery delays. If you have already received a delay notice, we start with the evidence review and the shape of the negotiation; if you are still pre-contract, we work with you from the clause design stage.

Has a factory just declared force majeure on you?

From reviewing the evidence and testing whether the delay period holds up, to clause design and settlement or termination negotiations
we step in before the loss grows

Phone   +82 10-9980-9959
Email   greenfrogseoul@gmail.com
KakaoTalk   pf.kakao.com/_XkfuX
Website   greenfrogseoul.com

Frequently Asked Questions

The factory is claiming force majeure because raw material prices went up. Is that valid?
A price increase on its own does not amount to force majeure. Under Chinese law force majeure means a circumstance that is unforeseeable, unavoidable and insurmountable, and something becoming more expensive is not performance becoming impossible, it is profit shrinking, which is a different thing entirely. The judgment changes if the government has blocked distribution and there is genuinely no material on the market, but price movement is treated as commercial risk. To eliminate this argument altogether, name raw material price fluctuations and currency fluctuations as exclusions in the force majeure definition in your contract.
If the factory gets a CCPIT force majeure certificate, is it off the hook?
The certificate confirms that the event occurred at a particular time in a particular area. It is supporting evidence, not a document that decides whether liability is excused. Whether that event actually blocked performance of this contract, and whether the delay being claimed matches the scale of the event, are things the factory still has to establish separately. When the document arrives, first compare the event period on it against the number of delay days the factory is asking for, and check that the area named matches where the factory sits. A five-day lockdown against a four-week delay means you can ask for an explanation of the rest.
If force majeure is established, is the deposit I already paid gone for good?
Force majeure is a mechanism that excuses liability for performing late. It does not create a right to keep money already received. If production ultimately becomes impossible and the contract is terminated, the principle is that the factory keeps only the amount corresponding to what it actually performed and returns the rest. In practice factories sometimes hold the deposit citing their own losses, so write the refund deadline and the deduction limit into the contract in advance. Cap the deduction at the actual cost of work in progress and buyer-specific raw materials verified by you, and give yourself the right to demand delivery of those goods, which widens how much you recover.